Phase 6 plan — closed
Phase 6 closed on 2026-11-16. Phase 7 is current. Read the Phase 6 close for every exit criterion, the owner decisions that changed the close gates, current cost reference, final fixes, idle capture and carried work. Forge Initiative f1ce7574-337a-485f-8a81-0938845523e8 retains the detailed Issues and closing comments.
Delivered stages
| Stage | Outcome and evidence |
|---|---|
| 6.1 Close the Phase 5 tail | Backup recovery, B1.9 retirement, legacy storage cleanup, R2-only new-byte enforcement, authority/idle fixes and benchmark harness corrections. Phase 5 close retains the starting obligations; data placement describes today's byte owners. |
| 6.2 Landing under contention | Exact-source conflict recovery, early resolution, shared/stacked checks, overtake and finish-wake recovery, and verified State/recipe preparation. Exit bench, release validation and zoo retain favorable and unfavorable observations. |
| 6.3 Bugs and friction | The pre-close paged inventory has 402 closed and 45 abandoned P6 Issues; only documentation close 53945141 remains in progress before its landing. The last wake, timing, zoo, friction-read and close-on-land Issues closed on 16 November. Explicitly moved follow-ups remain on their Phase 7 Items, listed in the close. |
| 6.4 Cost and agent surface | One hosted client mode, consolidated agent actions/CLI, bounded read-only records and conditional close-on-land. Terminal capsules, Work journal segments, indexed headers and request-local read reuse remove hot-path history and duplicate reads. Cost to serve records the measured reference and missing all-in allocation. |
| 6.5 Engineering health | Mechanical growth/cost and repeated-class guards, landing model/replays and public scenario evidence. The remaining regression ladder work stays on Phase 7 45f49fb7; no close-time benchmark is invented. |
| Design preparation | Art direction, design rules and mockups feed the Phase 7 product build; DESIGN.md remains the design authority. |
Exit decisions
The original exit required no open bug or core-claim Issue, every friction fixed or dropped, a B1.5d repeat with the conflict-recovery loss fixed and no regression, zero idle Convex calls and the agreed cost target. The owner's freeze rule distinguishes pre-freeze work from later core/severe bugs. Every incomplete line is now terminal with evidence or explicitly moved by the owner; the close names the disposition for each criterion.
The owner accepted the exit bench with its literal misses on 15 November: convoy N=16 per-task timing, strict N=10 correctness, recovery turns and incomplete comparison coverage remain disclosed. Published primary time to main, wall, CI and token results favor Forge at every N. Later validation is separate, not a headline replacement. Recovery and final overlap rechecks belong to 7d0ccd72 and 0a9df3cd in Phase 7.
The owner accepted going to market at the measured serving cost on 15 November instead of the earlier P6 target. The current reference is Professional $1.682603/1,000 with calls/compute included, or $4.201304/1,000 at full list. Storage and weekly backup/maintenance allocation remain unmeasured and need owner-only dashboard readings. The earlier billed 200-landing bar is a Phase 7 recheck on 686ecdde; no invoice or all-in price is claimed.
Growth at close
The close's node scripts/check-growth.mjs --print --machines reports phase start → close: tables 181 → 185, public error codes 501 → 484, agent actions 88 → 64, CLI commands 53 → 40, glossary terms 34 → 27, machine dependencies 0 → 0 and unreferenced exports 22 → 2. Current counts equal their ratchet baselines. Six hosted paths are guarded; per-change reasons remain in tests/growth-ledger/.
Handover to Phase 7
The close's carried-work table verifies each current Phase 7 parent and names the source-only sync gap, unexplained source action, flakes, workflow/preflight/import papercuts, regression ladder, cost/context rechecks and bulk owner-delete flow. The Phase 7 Initiative is 28591eeb-b74b-413a-ac41-1fef018b3dc1; read its current body and build-index comment before starting. Roadmap owns stage names and status describes capabilities.
Decisions retains tried-and-dropped alternatives and owner constraints; the lead rules, builder rules and workflow own delivery practice. The superseded open-acceptance table, old ordering and duplicate-triage draft have been removed from this plan; their history remains in source control and the original planning records. No scope, limit, production move, publication or outside-user trial is authorized by the close.